The Challenge
The offshore pump package required main equipment, operating accessories, commissioning spares, and a synchronized documentation package to meet the client technical requirements.
Supply of crude oil transfer pumps and associated accessories for the Kinh Ngu Trang - Kinh Ngu Trang Nam project.

Client
VIETSOVPETRO
Project Code
KNT-VT288
Location
Kinh Ngu Trang - Kinh Ngu Trang Nam Field Development, Block 09-2/09
Completion Date
Aug 27, 2024
The offshore pump package required main equipment, operating accessories, commissioning spares, and a synchronized documentation package to meet the client technical requirements.
TTE coordinated with Flowserve and supporting vendors to manage equipment readiness, photo records, packing, and handover documentation including COO, quality certificates, hazardous area certificates, MTC, calibration report, motor test report, and FAT report.
Completed handover of the Crude Oil Transfer Pump Package with equipment scope, operating accessories, and public-ready certification summaries suitable for website publication.
Main equipment and accessories controlled against oil and gas technical requirements.
Includes lubricant oil, barrier fluid, nitrogen charging kit, alignment tools, and commissioning spares.
Summarizes COO, COC/CQ, BV, hazardous area, MTC, calibration, motor test, and FAT documents.
TTE coordinated Flowserve and supporting vendors, controlled equipment readiness, standardized handover documentation, and prepared public-ready summaries of the technical certificates.
Aug 27, 2024
Pump package and certification summaries were handed over within the public-safe scope.
3
Unit
Flowserve
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
BV verification summary
BV verification summary
Summary of packing list and goods handover documentation.
Summary of origin, quality, material, and third-party compliance certificates.
Summary of FAT, motor test, calibration, and warranty documents.