The Challenge
The nitrogen generator package involved multiple principals and sub-vendors across mechanical, electrical-control, bottle rack, valves, instruments, and engineering documents that had to be synchronized before offshore deployment.
Supply of nitrogen generator, booster compressor, LCP, and supporting equipment for an offshore project.

Client
VIETSOVPETRO
Project Code
KNT-VT383
Location
Kinh Ngu Trang - Kinh Ngu Trang Nam Field Development, Block 09-2/09
Completion Date
Apr 8, 2025
The nitrogen generator package involved multiple principals and sub-vendors across mechanical, electrical-control, bottle rack, valves, instruments, and engineering documents that had to be synchronized before offshore deployment.
TTE managed the equipment list, coordinated multi-batch delivery, controlled site photo records, and standardized the handover documentation including manuals, drawings, datasheets, P&IDs, FAT/SAT procedures, certificate of offshore product, and related inspection reports.
Completed handover of the multi-principal Nitrogen Generator Package, including skid, compressor, LCP, bottle rack, valves, instruments, and public-safe handover documentation summaries.
Scope coordinated across Atlas Copco, Sauer/Mipec, DKE, and multiple supporting sub-vendors.
Combines nitrogen generator skid, booster compressor, bottle rack, and valve/manifold package.
Includes LCP, wiring/schematic, instrument list, and control monitoring safety signal summary.
Offshore document set grouped into manuals, drawings, datasheets, FAT/SAT, and compliance.
TTE managed the multi-principal scope, coordinated delivery batches, followed up with sub-vendors, standardized offshore document sets, and controlled handover records as public-safe summaries.
Mar 3, 2025
The first batch covered main and supporting items within the public-safe scope.
Mar 25, 2025
The next batch focused on booster compressor-related scope and associated items.
Apr 8, 2025
Completed remaining handover scope and offshore documentation summaries.
1
Unit
Atlas Copco
-
1
Unit
Sauer/Mipec
-
1
Unit
DKE
-
1
Unit
-
-
1
Unit
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Installation, start-up, commissioning, and performance curve documentation.
Summary of GA drawings, P&IDs, wiring, logic, and electrical distribution documents.
Datasheets for skid, compressor, LCP, bottle rack, valves, and instruments.
Summary of FAT/SAT procedures, FAT report, certificate of offshore product, and quality certificates.